Friday, February 18, 2011

Week 18: Siding


Between three snowstorms (two blizzards,) Three illnesses (including Type A Influenza,) and Stephen working at his job on weekends, not much has been done. The work completed could've been done in a productive weekend, so I'll compress it. We put up siding on the entire back of the house and most of the front. To reach over the garage hoods will require the boom lift. We bought a scissor-type tool to cut the cement board, and it's AWESOME.

Tuesday, December 28, 2010

Cleanup

It was Christmas, so we held off on the big stuff this weekend and took time out to put on temporary carriage doors, install door hardware, and clean and sort the inside of the shop/garage. Now we can work inside and store stuff without fear of theft! Awesome.

Thursday, December 23, 2010

Week 17: Siding

We put up siding. It is pre-primed HardiePlank. It is scored with a box cutter and then it breaks at the score. Very easy to work with. We got the gable ends done up about as far as could be done without the boom lift. The job took a great deal more time than expected largely due to the time lost marking lines and studs, moving scaffolding, etc.

Monday, December 6, 2010

Week 16: Trim Saga Finale


Stephen put up misc. trim, roofing and flashing to get us ready for siding next week. We still couldn't get the boom lift to do the gable trim, so it will have to be done at the same time as the top gable siding.

Much of the weekend was spent trying to locate siding and discussing options.

I primed half of the rafters that will remain exposed in the apartment.

Wednesday, December 1, 2010

Week 15: Thanksgiving

For the four day weekend, we had planned to get a boom lift to get into the gables to put up trim, but they didn't have any available. Instead, we put up the eyebrows, primed and tar-papered them, and Stephen trimmed out the cornices and soffits on the non-gabled sides of the house. The soffits are a foot deep, and the trim extends a foot below the soffit. The trim detail (dentil blocks, etc) will be added later. Stephen also added a pediment hood over the apartment door entrance.

We got the door hardware for the apartment entry from Ebay this week, some cool old handmade wrought iron stuff.

The trim has taken much longer than expected, and it's getting cold here. It looks like we'll be finishing the exterior about four weeks behind schedule.

Week 14: Door Trim and Eyebrows

On week 14, Stephen built the door trim, including the doorways that don't yet have doors. He finished up the cornice returns.

He also built the half-elliptical hoods for the carriage doors (eyebrows.) I built none, but designed both the look and the construction method. Two arches were cut out of plywood for each set of carriage doors, then the plywoods were connected by pieces of 2"X6" and covered on the top with OSB with kerfs cut into the top to allow it to bend. They will eventually be covered with copper.

Monday, November 15, 2010

Week 13: Window Trim


Later picture shows window trim and cornice returns
Stephen trimmed out the windows with 2"X6" and 2"X4" treated pine. He had considered cedar, but decided against it because the chance of getting long enough pieces in excellent condition was unlikely at best, and cost prohibitive at worst. This means we will not be able to paint the trim until next year.